Process an empty pallet instruction

Related topics

You will be given a pick instruction telling you in which location there is an empty pallet that should be moved.

The following describes the processing of an R/F batch that includes one empty pallet instruction line. If your batch includes several lines, then you will have to process all lines in the batch.

  1. Select the Select R/F activity menu item.
  2. On the main panel, select the Picking activity.
  3. You access Select R/F batch. Select the batch you want to work with.
  4. The Empty pallet window is displayed. Complete the following fields:
  5. Zone
    Enter the zone from which the empty pallet is picked.
    Location
    Enter the location from which the empty pallet is picked.

    Click OK. Exit the routine.