This program is used to maintain the work centre capacity that differs from the base calendar that is connected to the work centre. From this panel you can override the work centre parameters to calculate the day total capacity.
More information can be made available on the panel via the DC1 UI Client Edit columns feature. This feature also allows you to customize the panel to only show the information you want.
Note: This function is based on the generated work centre capacity file. The panel will display header information without capacity dates if the capacity has not been generated. If so, click Re-create capacity.
Options
Function keys
Selection fields
- Work centre
- The code and description that identify the work centre.
- Workl planning type
- The type of operation time that is included in the workload, either Run/labour or Machine. The information is retrieved from the Workl planning type field in the Work centre table.
- Date
- The date for the capacity.
- Capacity
- The gross capacity per resource. This information is retrieved from the calendar connected to the work centre.
- New cap
- The capacity that is divergent from the calendar. If blank, you can enter a new capacity. Note: You cannot set the new capacity if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file, since the total capacity for the day time is set-up in the day format.
- Chg until
- The date indicates until when the entered work centre total capacity calculation parameters will be valid. After the entered date the parameters will be overridden by the normal work centre parameters.
- Reduced
- The amount of hours indicate with how much time the day capacity is planned to be reduced according to planned preventive service. Note: The reduced time is the planned service time related to the number of shifts.
- Day cap
- The gross capacity for the work centre for a specific date.
- Net cap
- The net capacity for the work centre (gross capacity reduced with efficiency factor) for a specific date.
- Rstgr
- The workload restriction group that is connected to the work centre date. If several restriction groups are connected to the same date, this field displays the first group followed by <+>. The restriction groups control if the date is valid for planning a specific product. Note: The restriction group can only be used for work centres defined as critical resources.
- Scheme
- The scheme used for capacity creation. This field is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.