Work with shortage analysis, Manufacturing (REQ027B)

In this program is to work with shortage analysis proposals for manufacturing orders.

On this panel selected items for the current proposal are displayed in sequence by shortage code.

Options

Order release Select this option to release an order. Use this option if you do not want to the display the Manufacturing order creation panel for a new order. When a preliminary order is released, the connected sales order line is also released and updated with a new dispatch date is changed.
Order maint Select this option to maintain the manufacturing or purchase order.
Detail Select this option to maintain/view detailed information.
Time axis Select this option to view the time axis.
Mtrl/cap clearance Select this option to view the material and capacity clearance.
Periodical stat Select this option to view periodical statistics.
Release (prompt) Select this option to release an order. Use this option if you want to the display the Manufacturing order creation panel in order to change some information before a new order is created.
Crt pur order Select this option to create a purchase order directly for an item that is normally produced internally.

Function keys

Priority View the priority analysis for the current proposal.
Batch clearance Access the batch clearance selection panel.
Manufacturing order Maintain manufacturing orders.
Proposal
Warehouse
Production hours
The result of production hours calculations for selected items.
Item
Unit
The stock or structure unit of the item. See Structure unit handling for more information.
Order quantity
The proposed order quantity. This is set to EOQ, Economic Order Quantity, when the proposal is created. You can change the quantity on the detail panel.
Short quantity
The shortage quantity (total shortage within lead time considering the order period).
Short date
The shortage date. This date will be used as completion date of the manufacturing order when released. You can change the date on the detail panel.
S c
The shortage code.
S-order
The number of the connected sales order number.
M-order
The manufacturing order number for a preliminary or released order.
P-order
The purchase order number for a released order.