In this program is to work with shortage analysis proposals for manufacturing orders.
On this panel selected items for the current proposal are displayed in sequence by shortage code.
Options
| Order release | Select this option to release an order. Use this option if you do not want to the display the Manufacturing order creation panel for a new order. When a preliminary order is released, the connected sales order line is also released and updated with a new dispatch date is changed. | 
| Order maint | Select this option to maintain the manufacturing or purchase order. | 
| Detail | Select this option to maintain/view detailed information. | 
| Time axis | Select this option to view the time axis. | 
| Mtrl/cap clearance | Select this option to view the material and capacity clearance. | 
| Periodical stat | Select this option to view periodical statistics. | 
| Release (prompt) | Select this option to release an order. Use this option if you want to the display the Manufacturing order creation panel in order to change some information before a new order is created. | 
| Crt pur order | Select this option to create a purchase order directly for an item that is normally produced internally. | 
Function keys
| Priority | View the priority analysis for the current proposal. | 
| Batch clearance | Access the batch clearance selection panel. | 
| Manufacturing order | Maintain manufacturing orders. | 
- Proposal
 
- Warehouse
 
- Production hours
 - The result of production hours calculations for selected items.
 
- Item
 
- Unit
 - The stock or structure unit of the item. See Structure unit handling for more information.
 
- Order quantity
 - The proposed order quantity. This is set to EOQ, Economic Order Quantity, when the proposal is created. You can change the quantity on the detail panel.
 
- Short quantity
 - The shortage quantity (total shortage within lead time considering the order period).
 
- Short date
 - The shortage date. This date will be used as completion date of the manufacturing order when released. You can change the date on the detail panel.
 
- S c
 - The shortage code.
 
- S-order
 - The number of the connected sales order number.
 
- M-order
 - The manufacturing order number for a preliminary or released order.
 
- P-order
 - The purchase order number for a released order.