The purpose of this program is to give an overview of the planned and actual totals of the different cost codes for the selected phase.
The Project cost control enquiry provides the user with an overview of the actual situation of the project and the selected phase from the cost price’s perspective.
Total net sales value, tied capital, planned cost and actual cost price are displayed for each cost code of the selected project phase. The differences between planned and actual costs are also displayed. The forecast cost can also be entered.
The totals are updated at run time when a price of a detail line is changed (i.e. maintenance programs, project product costing, services and activities reporting, purchase order reception, production order reception). This means that no special calculation function is necessary.
Function keys
- Customer
- The customer of the project/quotation.
- Status
- The code indicates the status of the project/quotation.
- Project
- Currency
-
- Exch rate
- The exchange rate of the project.
- Description
- The description of the project.
- Total Proj
- The total values of the whole project.
- Phase
- The selected phase and description.
- Tot Phase
- The total values of the selected phase of the whole project.
- Cost code
- The cost code. One line per cost code with the total values is displayed.
Panel modes
Depending on the active mode, this panel displays sales, invoicing or costing values per cost code for the selected phase. Click the links below to view what fields are displayed in each mode.
Sales prices mode
Invoicing mode
Costing mode