Related topics
This program is used to report start and stop for manufacturing operations. In attesting this program is used only to report start of an activity.
- Employee
- Date
- Displays the date for start or stop.
- Time
- Displays the time for start or stop.
- Work group
- A work group code and a description are displayed if the program is used for reporting group order.
- Stop operation
- The order, the operation number and the work code are displayed if you have an ongoing operation. The activity will be stopped when you click OK.
- Quantity approved
- Only shown if you have an ongoing operation. Enter approved quantity for the operation.
- Quantity rejected
- Only shown if you have an ongoing operation. Enter rejected quantity for the operation.
- Reason code
- Only shown if you have an ongoing operation. Enter a reason code, from Work with reason codes, for the operation.
- Completed
- Only shown if you have an ongoing operation and you have authority to report operation complete. Indicate if the report operation is completed. Note: Reporting an operation as completed cannot be done if another employee is working with the operation.
- Start operation
- Enter the order, the operation number and the work code if you want to start a new activity. If the work code of the ongoing operation is setup time, the fields are predefined to start run/labour time for the same operation.
- cost centre
- Enter a code from Work with cost centres, if the activity is to refer to another cost centre than the default cost centre attached to the work centre. If the work code of the ongoing operation is setup time, the cost centre for the run/labour time will be defaulted to that used for the setup time.
- Work centre
- Only shown if you have authority to change work centre for operations. Enter a code from Work with work centres – TME to change work centre for the operation. This is not allowed if the operation previously has been started. If the work code of the ongoing operation is setup time, the work centre for the run/labour time will be defaulted to that used for the setup time.