Create the day scheme to be attached to a work centre

Related topics

Via this panel, the working interval and all the breaks are defined, besides man factor and number of machines. If any information, related to man factor and/or machines, is entered then this information will override the information that is available at the work centre.

Note: To run this program, the MPL-TIME (Plan operation by date/time) function must be activated in the Function control file; otherwise the system will generate an error message.

  1. Select the Work centre day schemes menu item.
  2. You access Work with work centre day schemes. Click Add to create the day scheme for the work centre.
  3. You access Work centre day scheme maintenance. Complete the following fields:
  4. Day scheme
    Enter the day scheme id. It is the description of the working day. It consists of a working interval and breaks.
    Description
    Enter a description of the day scheme.
    Work hours
    Enter the working interval (from and to) in the HH:MM format.
    Lunch
    Enter the interval break for lunch time in the HH:MM format.

    See the Panel help for information about the remaining fields.

    Click OK to add the day scheme. Exit the routine.