Via this panel, the working interval and all the breaks are defined, besides man factor and number of machines. If any information, related to man factor and/or machines, is entered then this information will override the information that is available at the work centre.
Note: To run this program, the MPL-TIME (Plan operation by date/time) function must be activated in the Function control file; otherwise the system will generate an error message.
- Select the Work centre day schemes menu item.
- You access Work with work centre day schemes. Click Add to create the day scheme for the work centre.
- You access Work centre day scheme maintenance. Complete the following fields:
- Day scheme
- Enter the day scheme id. It is the description of the working day. It consists of a working interval and breaks.
- Description
- Enter a description of the day scheme.
- Work hours
- Enter the working interval (from and to) in the HH:MM format.
- Lunch
- Enter the interval break for lunch time in the HH:MM format.
See the Panel help for information about the remaining fields.
Click OK to add the day scheme. Exit the routine.
Related topics
- About work centres
- Create a work centre
- Create work centre capacity
- Change the capacity for a work centre
- Change the work centre parameters
- Maintain the day scheme for a work centre
- Create work centre scheme groups
- Attach a day scheme to the working days in a work centre
- Set up a workload restriction group
- Add workload restrictions to a work centre
- Create a work centre capacity simulation version
- Simulate the capacity for a work centre
- Activate future work centre prices
- Delete a work centre